Order in Appeal 19 of 2015

Summary: 

Ferro alloy unit -- Challenging levy of deemed consumption charges on the ground that the DISCOM had not been able to supply uninterrupted power during the full year i.e., on annual basis -- Hon’ble Commission passing an order that such charges cannot be levied when the DISCOM is not in a position to supply power uninterruptedly -- Appeal disposed of on mutual request of the appellant and respondents directing the respondents to implement the Hon’ble Commission’s orders